How to calculate SMV for garment operations, with a worked example
SMV (standard minute value) is the time a trained operator needs for one operation at a normal pace, plus allowances. You calculate it by timing the operation, adjusting for the operator's pace and adding allowances for fatigue and delays.
The formula
SMV = observed time × performance rating × (1 + allowance)
- Observed time: the average time of several timed cycles, in minutes
- Performance rating: the operator's pace compared with a normal pace (100% = normal)
- Allowance: extra time for fatigue, personal needs and small delays, often 12% to 20% in sewing
Worked example: attach pocket
- Time ten cycles. The average is 0.40 minutes.
- Rate the operator at 110%, because they are working faster than normal. Basic time = 0.40 × 1.10 = 0.44 minutes.
- Add a 15% allowance: 0.44 × 1.15 = 0.506.
- SMV for attach pocket ≈ 0.51 minutes.
Repeat for every operation and add them up for the garment's total SMV.
What SMV is used for
UseHow
Hourly target
60 ÷ SMV × operators × target efficiency
Line efficiency
(pieces × SMV) ÷ (operators × minutes) × 100
CMT price
SMV × cost per minute ÷ expected efficiency
Line balancing
Group operations so each station has a similar SMV load
Common mistakes
- Timing too few cycles, or only the fastest operator
- Forgetting to rate performance, which bakes one person's speed into the standard
- Using last season's SMV after the method or machine changed
- Copying SMVs from another factory with different equipment
Doing it faster
A stopwatch study and the arithmetic take hours per style. Quick OB records each cycle with a tap on a phone and calculates SMV immediately, then builds the operation bulletin and hourly targets from it. AI Enterprises reported 70% faster planning after making this change.
FAQs
Questions about this topic
Something else on your mind? Call +91 98408 99559 or write to sales@asktek.net.
Is SMV the same as SAM?
Yes. SMV (standard minute value) and SAM (standard allowed minute) describe the same measure.
What allowance should I use?
Many sewing floors use 12% to 20%. Use your company's or buyer's standard and keep it consistent across styles.