What is SMV (standard minute value)?
SMV in one line
SMV is the time, in minutes, that a trained operator working at a normal pace needs to complete one garment operation, including allowances for fatigue and personal needs.
Also called: SAM, standard allowed minute
SMV is calculated from a time study: the observed time for an operation is adjusted by the operator's performance rating to get basic time, then increased by allowances. A simple T-shirt might total 6 to 9 minutes across all operations, while a lined jacket can be well over 60.
Factories use SMV to price CMT work, set hourly targets, balance lines and measure efficiency. If the SMV is wrong, every target and every efficiency figure built on it is wrong too, which is why it should be recalculated when the method changes.